**Flowchart: Data Center Network & Infrastructure Handover Process**
```
Start
|
v
Receive Handover from Design Team
|
v
Data Center Network & Infrastructure Verification
-----------------------------------------
| Hosting Request Project Name & Number |
| Data Center Location (Riyadh, Dammam, Jeddah) |
| Data Center Name & Exact Rack Location |
| Approved Hosting Form |
| LLD & HLD documents |
| Complete end-to-end cable mapping |
| Initial Backup Configuration |
| Cyber Security & Vulnerability Checks |
| Verify Blade Server Environment Type |
| Verify Naming Conventions |
| iSecure Registration |
-----------------------------------------
|
v
Forward to Hardware Support Team
-----------------------------------------
| Validate all Information |
| Vendor Support Details verification |
| Verify SAID & Contract Number |
| Verify System & Application Owner |
| NAR Request for Management IPs |
| Verify Admin Access Credentials |
| Firmware Version Check |
| Perform Physical Health Check |
| Boot Disk Redundancy Validation |
| BMC TrueSight Monitoring Status |
| Vendor Monitoring Status |
-----------------------------------------
|
v
--------------------------------------
| |
v v
Forward to DCM Operations Forward to Storage Operations
-------------------------------------- --------------------------------------
| Verify cabling as per DCM Standards | | Verify WWPN Connections |
| Verify Labeling for All Cables | | Verify HBA Speed |
| Report Snags in Chassis or Cabinet | | Check Uplink Port Speed (16GB/32GB) |
| Clearance Certificate & Approval | --------------------------------------
-------------------------------------- |
| |
--------------------------------------
|
v
Final Verification
-----------------------------------------
| Ensure All Previous Verifications Done |
-----------------------------------------
|
v
Accept Handover & Complete
```